Computation of quantity and the its cost is given below for this planed community hall.............i hope this will be helpful for vishwakarma yojana students........
It is designed for a village having population around 15000.
It
contains one central hall with two multi-purpose room (can be used as kitchen)
and one office.
Except it contains
four rooms for residential purpose, two large size storage rooms for various
storage purposes. There are two toilets blocks separate for men and women. It
also have large ground open to sky which serves for various purposes and also
have parking facility for comfort of their users.
We designed the hall
in staad pro software in which following dimensions are taken as design
dimension.
Beams 0.3*0.6 and
0.4*0.6.
Columns 0.4*0.6
Measurement Sheet
Sr no
|
Item of work
|
no
|
L
m
|
B m
|
D/ H m
|
QUANTITY
|
1
|
Excavation in foundation for columns
|
37
|
0.7
|
0.9
|
0.7
|
16.31 m3
|
2
|
BBLC work in foundation
|
37
|
0.7
|
0.9
|
0.2
|
4.662 m3
|
3
|
Masonry work
| |||||
1 st footing
|
37
|
0.6
|
0.8
|
0.2
|
3.552
| |
2 ND footing
|
37
|
0.5
|
0.7
|
0.2
|
2.59
| |
3 rd. footing
|
37
|
0.4
|
0.6
|
0.1
|
0.888
| |
7.03 m3
| ||||||
4
|
Masonry work in super structure
|
1
|
304.6
|
0.2
|
3
|
182.76 m3
|
5
|
RCC work for all columns
|
37
|
0.4
|
0.6
|
3
|
26.64 m3
|
6
|
External plaster
|
1
|
152
|
-
|
3
|
456 m2
|
7
|
Internal plaster
|
1
|
462
|
-
|
3
|
1386 m2
|
8
|
RCC slab work
|
1
|
50
|
26
|
0.1
|
130 m3
|
9
|
Steel work
| |||||
In slab
[(130*1)/100]*78.5
=102.05 q/m3=1025 kg
|
1025 kg
| |||||
In column
[(26.64*1)/100]*78.5
=20.91 q/m3=2091 kg
|
2091 kg
| |||||
10
|
Parapet wall
|
1
|
152
|
-
|
0.6
|
91.2 m2
|
Abstract Sheet
Sr No.
|
Items
|
Quantity
|
Unit
|
Rate
Rs
|
Amount
Rs
|
1
|
Earthwork in Excavation for columns including labour and machinery
|
16.31 m3
|
cum
|
205
|
3343.55
|
2
|
B.B.L.C in Foundation Base(1:3:6)
|
4.662 m3
|
cum
|
2604
|
12139
|
3
|
Brickwork in foundation up to plinth
|
7.03 m3
|
cum
|
3190
|
22481.94
|
4
|
R.C.C work 1:2:4 in columns
|
26.64 m3
|
cum
|
4937
|
131521.7
|
5
|
R.C.C work 1:2:4 in slabs and chajja fair finished excluding steel reinforcement and its bending but including centring and shuttering and binding steel- and labour work
|
130 m3
|
cum
|
4937
|
641810
|
6
|
Mild Steel including reinforcement in R.C.C works in slab
|
1025 kg
|
Kg
|
54.87
|
56241.75
|
In column
|
2091 kg
|
kg
|
54.87
|
114733.17
| |
7
|
1st Class Brickwork in 1:6 cement mortar:
|
304.6 m3
|
cum
|
3321
|
60676.32
|
8
|
12mm inside Plaster in 1:6 cement mortar
|
1386 m2
|
Sq. m
|
100
|
138600
|
12mm outside Plaster in 1:6 cement mortar
|
456 m2
|
Sq. m
|
130
|
59280
| |
9
|
Painting two coats over one coat of priming:
|
1842 m2
|
Sq. m
|
20
|
36840
|
10
|
Brickwork in parapet wall
|
91.2
|
Cum
|
399
|
38388.8
|
Total =1358732
| |||||
3% Contingencies = 40800
| |||||
2% Work charged Establishment = 27170
| |||||
Add 8% for water supply works and sanitary works
=108700
| |||||
Grand Total = 1535402
Say 15, 35,500 rs.
|