COMMUNITY HALL

Computation of quantity and the its cost is given below for this planed community hall.............i hope this will be helpful for vishwakarma yojana students........


It is designed for a village having population around 15000.


It contains one central hall with two multi-purpose room (can be used as kitchen) and one office.
Except it contains four rooms for residential purpose, two large size storage rooms for various storage purposes. There are two toilets blocks separate for men and women. It also have large ground open to sky which serves for various purposes and also have parking facility for comfort of their users.

We designed the hall in staad pro software in which following dimensions are taken as design dimension.
Beams 0.3*0.6 and 0.4*0.6.
Columns 0.4*0.6

Measurement Sheet

Sr no
Item of work
no
L
m
B m
D/ H m
QUANTITY
1
Excavation in foundation for columns
37
0.7
0.9
0.7
16.31 m3







2
BBLC work in foundation
37
0.7
0.9
0.2
4.662 m3







3
Masonry work






st footing
37
0.6
0.8
0.2
3.552 

ND footing
37
0.5
0.7
0.2
2.59

rd. footing
37
0.4
0.6
0.1
0.888






7.03 m3







4
Masonry work in super structure
1
304.6
0.2
3
182.76 m3







5
RCC work for all columns
37
0.4
0.6
3
26.64 m3







6
External plaster
1
152
-
3
456 m2







7
Internal plaster
1
462
-
3
1386 m2







8
RCC slab work
1
50
26
0.1
130 m3







9
Steel work






In slab
[(130*1)/100]*78.5
=102.05 q/m3=1025 kg




 1025 kg

In column
[(26.64*1)/100]*78.5
=20.91 q/m3=2091 kg




 2091 kg







10
Parapet wall
1
152
-
0.6
91.2 m2
Abstract Sheet

Sr No.
Items
Quantity
Unit
Rate
Rs
Amount
Rs
1
Earthwork in Excavation for columns including labour and machinery  
16.31 m3   
cum
205
3343.55
2
B.B.L.C in Foundation Base(1:3:6)
4.662 m3   
cum
2604
12139
3
Brickwork in foundation up to plinth
7.03 m3
cum
3190
22481.94
4
R.C.C work 1:2:4 in columns
26.64 m3
cum
4937
131521.7
5
R.C.C work 1:2:4 in slabs and chajja fair finished excluding steel reinforcement and its bending but including centring and shuttering and binding steel- and labour work
130 m3
cum
4937
641810
6
Mild Steel including reinforcement in R.C.C works in slab
1025 kg
Kg
54.87
56241.75

In column
2091 kg
kg
54.87
114733.17
7
1st Class Brickwork in 1:6 cement mortar:
304.6 m3
cum
3321
60676.32
8
12mm inside Plaster in 1:6 cement mortar
1386 m2
Sq. m
100
138600

12mm outside Plaster in 1:6 cement mortar
456 m2
Sq. m 
130
59280
9
Painting two coats over one coat of priming:
1842 m2
Sq. m 
20
36840
10
Brickwork in parapet wall
91.2
Cum
399
38388.8


Total =1358732




 3% Contingencies = 40800


2% Work charged Establishment = 27170


Add 8% for water supply works and sanitary works
=108700


Grand Total = 1535402
Say 15, 35,500 rs.